MINING OF Limestone from their Mines at Babupur, District Satna in the state of MP and intends to outsource its Limestone raising activities leading to onwards dispatch to designated area/limestone, crusher in the Cement Plant at Babupur, District Satna, Madhya Pradesh vide Work Order Agreement dated 29.09.2009
Organization
:
BHILAI JAYPEE CEMENT LIMITED
Estimated (Rs. In Lacs)
:
13,446.00
Start Date
:
01-09-2009
Completion
:
01-09-2020
Scope of work
:
Mining of Minor Mineral Quarries of Road Metal and Masonry Stones and related activities given in the Atela Kalan Mines in Tehsil Charkhi Dadri, District Bhiwani, Haryana. Transportation of Rock Boulders at the atela Kalan Mines in Tehsil Charkhi - Dadri Dist Bhiwani, Haryana vide Work Order No. MSK/Mine/MKEPL/2015-16/01 dated 01.06.2015.
Organization
:
MSK - JV
Estimated (Rs. In Lacs)
:
30,240.00
Start Date
:
01-06-2015
Completion
:
01-06-2021
Scope of work
:
Drilling & Blasting towards generation of Builders sized between 05 mm to < 500 mm, at Bangalore plant in Urugahalli, Bidadi Hobli, Ramnagaram District, Karnataka vide Work Order No. UIMPL/WO/001 to 003 dated 10.06.2015
Organization
:
UNITED INFRA MINERALS PVT LTD
Estimated (Rs. In Lacs)
:
2,658.00
Start Date
:
01-06-2015
Completion
:
01-06-2020
Scope of work
:
Quarrying of Rock BOULDER, Drilling, Blasting, Sizing, Face Cleaning, Loading into Dumper, Sizing (-700 mm), (ii) Removal of Top soils / over burden / weather or fractured rock from the boulders extracted at Mouja - Jagannathpur, Kosma, PO+PS - Chandouti, District Gaya, Bihar vide Work Order no. RS/MKEPL/001 to 002 dated 27.04.2016.
Organization
:
RAJENDRA SINGH MINES
Estimated (Rs. In Lacs)
:
5,760.00
Start Date
:
01-05-2016
Completion
:
01-07-2020
Scope of work
:
Hiring of Excavator with Dumpers / Tippers for Job work (Excavator / Loading & over burden removal) at Khertala Mines, District Pali, Udaipur, Rajasthan vide Work Order no. WI-INDS/2011-12 dated 24.10.2011. Hiring of Excavator with Dumpers / Tippers for Job work (Excavation / Loading & over burden removal) at Rabach Mines, vide Work Order No. WIL/Tr. Contract/2011-12 dated 24.10.2011.